Today to explain to you about the cooling tower of the cooling tower installation sequence
2016-12-05 09:46:39http://www.szdxj.com admin

East Star cold water machine - cooling tower installation sequence

——Simple installation procedure for cooling tower

The installation position of the cooling tower needs to pay attention to the ventilation condition and the bearing capacity of the floor.

Pre super cement base, and installation of cooling tower support frame.

          In accordance with the instructions, - concrete and steel frame foundation, and then the cooling tower chassis to support ring assembled into a frame shape, the level must be unified. Here to note: naser-80 above the central position of the central foundation can not be ignored.

         Installation of cooling tower water tank and chassis:

    The tank is arranged to the central basin on the basis of the fixed sink peripheral flange.

    The sealing body between the basin and surrounding joints;

    The water tower is a multi combination type, the installation is completed, need to prepare the fiber mortar sealing joint. Above 60T.

    Install overflow device, the floating ball combination and strainer;

    The overflow device, the floating ball combination and strainer placed in the preset place, be wrapped hose joint tape in laryngeal teeth.

    Installing central tube, central tube bundle and body support frame;


         The throat of the center is to be installed vertically on the throat of the water tank, and then the central pipe is arranged on the central pipe bundle. ZLC need to install the sound insulation seats in the loading support.

    Installation of heat sink and heat sink;

    The heat sink bracket is connected to the central tube bundle, but it must ensure the horizontal vertical. Verify that the parts are in series with screws, and then put the combined heat sink. Note: if you need to step on the frame to install other equipment, please first board temporary pad in the cooling bracket.

    Installing outer shell body and climbing ladder;

    The outer shell body is arranged on the body support frame, and the radiating fins are assembled and tightened. In the early development of installation on the support ladder.

Installation of sprinkler pipe appliances and water spray pipe;

          The nozzle is arranged in the center tube top, then the set of utensils hanging tube in the nozzle, the water pipe in the horizontal propulsion nozzle, the use of force, pull hook, tension control, until the water pipe into the horizontal position. The water spray hole and the vertical line to 10 degrees backward installation. (at the time of operation, at the end of the training point of view.)

Install motor, motor frame and fan;

         The motor frame is horizontal at the top of the casing body, and then put into the motor and reducer, the current distribution of fan combination, and finally with the fan net and belt cover.

Note: the following 80 towers to pre installed motor, motor frame and fan combination was put on.

          More than 100 of the fan angle according to the demand of air and set the tone for the school.

          Need to install the hairdryer after installing the motor, the motor frame and the fan, and then install silencer.

Installed in the ventilation network:

          The net flat wind in the gap between the pillar and the pillar on the plastic screw can be tightened.

Note: need to install sound insulation wind skirt.

          Want to know more about the cold water machine screw chiller - water cooling machine - pharmaceutical machinery with cold water chiller - machine - plating machine - open air cooled chillers - temperature machine - chiller tower - scroll chiller - explosion-proof chiller chiller - acid - corrosion - cold water machine--

Our web site is http://www.szdxj.com

24小时服务电话:400-041-8118

销售专线:13923464030

公司电话:0755-81715045  0755-81715587

公司传真:0755-81715085

公司邮箱:szwj1688@163.com

公司官网:www.szdxj.com www.szdxzl.cn

工厂地址:深圳市龙华区观澜樟坑径下围工业区一路东星产业园


  • official micro letter

  • official microblogging

Feedback在线留言
Copyright; Shenzhen City, East Star Refrigeration Technology Co., Ltd. Guangdong -2 09046816 ICP